
Village Restoration Project, Dharampani
Till Mansir 24 th , 2073 (Dec 9 th of 2016)
Group 1: Completed 12 HHs:
In the First Phase of the Reconstruction Project, so far total 12 houses completed with 13 families are beneficiaries, remaining wood works including fixing window/doors covers and “Baranda”.
Group 2: Construction Work started:
In the Second Phase of the Reconstruction Project, the construction work has been starting since Nov 15th of 2016, four houses are under construction fixing windows/doors in ground floor.
Group 3: Dismantled old damaged House:
Dismantled one old damaged house of the needy family, more than 30 members of the community involved during dismantling work.
{{ 'Comments (%count%)' | trans {count:count} }}
{{ 'Comments are closed.' | trans }}