Collage

Village Restoration Project, Dharampani

Till Mansir 24 th , 2073 (Dec 9 th of 2016)

Group 1: Completed 12 HHs:

In the First Phase of the Reconstruction Project, so far total 12 houses completed with 13 families are beneficiaries, remaining wood works including fixing window/doors covers and “Baranda”.

Group 2: Construction Work started:

In the Second Phase of the Reconstruction Project, the construction work has been starting since Nov 15th of 2016, four houses are under construction fixing windows/doors in ground floor.

Group 3: Dismantled old damaged House:

Dismantled one old damaged house of the needy family, more than 30 members of the community involved during dismantling work.

{{ message }}

{{ 'Comments are closed.' | trans }}